Carolyn and I arrived at the SpaceFarm around 12:00pm. The day was overcast, slightly windy, and the temperature was in the mid 30’s. We worked Saturday and Sunday and spent the night with my aunt and uncle. It was a cold and labor intense visit; we focused on cleaning and prepping the unit for remodel.


List of progress

• Inspected propane lines and plumbing
• Swept up mouse droppings and rat poison
• Scrubbed mold out of refrigerator
• Sanitized microwave, sinks, counters, and toilet
• Tore our bathroom wall and wardrobe out
• Removed and cleaned furnace ducts
• Removed bathroom sink
• Remove kitchen counter, sink, and stove


Tools and Supplies

• Cordless driver drill
• Philips/flathead bit
• 11/64 metal drill bit (to drill out rivets in walls and wardrobe)
• Hand philips screwdriver
• Hand flathead screwdriver
• Hammer
• Five-in-one
• Utility knife
• W-D 40
• Contractor quality trash bags
• Mop and bucket
• Bleach
• Tool box
• Keys
• Broom
• Dustpan

Carolyn at the beginning of the day


Kitchen counter before its removal

After removing range and oven

Yeah!

Me disconnecting pipes from sink

Sink is removed



Kitchen Counter Removed


Furnace and converter mess- will need to replace




The makeshift workshop


Bathroom wall removed





Bathroom counter removed


Shower partition removed





Shower Removed


Water Heater